Multi Stage Cementing Operation


When a long intermediate string of casing is to be cemented it is sometimes necessary to split the cement sheath in the annulus into two to conduct the job usually using multi stage cementing operation job , with one sheath extending from the casing shoe to some point above potentially troublesome formations at the bottom of the hole, and the second sheath covering shallower troublesome formations.

multi stage cementing operation procedure

multi stage cementing procedure

The placement of these cement sheaths is known as a multi stage cementing operation (see picture multi stage cementing). The reasons for using a multi-stage operation are to reduce:
• Long pumping times
• High pump pressures
• Excessive hydrostatic pressure on weak formations due to the relatively high density of cement slurries.

The procedure for conducting a multi stage cementing operation is as follows:

First stage
The procedure for the first stage of the operation is similar to that described in single stage cementing , except that a wiper plug is not used and only a liquid spacer is pumped ahead of the cement slurry. The conventional shut-off plug is replaced by a plug with flexible blades. This type of shut-off plug is used because it has to pass through the stage cementing collar which will be discussed below. It is worth noting that a smaller volume of cement slurry is used, since only the lower part of the annulus is to be cemented. The height of this cemented part of the annulus will depend on the fracture gradient of the formations which are exposed in the annulus (a height of 3000′ – 4000′ above the shoe is common).
Second stage
The second stage of the operation involves the use of a special tool known as a stage collar (see multi stage cmenting collar),

multi stage cementing collar picture

multi stage cementing collar picture

which is made up into the casing string at a pre-determined position. The position often corresponds to the depth of the previous casing shoe. The ports in the stage collar are initially sealed off by the inner sleeve. This sleeve is held in place by retaining pins. After the first stage is complete a special dart is released form surface which lands in the inner sleeve of the stage collar. When a pressure of 1000 – 1500 psi is applied to the casing above the dart, and therefore to the dart, the retaining pins on the inner sleeve are sheared and the sleeve moves down, uncovering the ports in the outer mandrel. Circulation is established through the stage collar before the second stage slurry is pumped.

The normal procedure for the second stage of a multi stage cementing operation is as follows:

1 Drop opening dart
2 Pressure up to shear pins
3 Circulate though stage collar whilst the first stage cement is setting
4 Pump spacer
5 Pump second stage slurry
6 Release closing plug
7 Displace plug and cement with mud
8 Pressure up on plug to close ports in stage collar and pressure test the casing.

To prevent cement falling down the annulus a cement basket or packer may be run on the casing below the stage collar. If necessary, more than one stage collar can be run on the casing so that various sections of the annulus can be cemented. One
disadvantage of stage cementing is that the casing cannot be moved after the first stage cement has set in the lower part of the annulus. This increases the risk of channelling and a poor cement bond.

After primary single stage and multi stage cementing more critical cementing job will be discuss on our site. Cementing liner is one of critical cementing operation, so stay with our site. Thanks